- Peer Review
-
A review of your work by another with similar knowledge or experience in the same or a closely related field. [D05035]
|
SU |
-
A review of products or services, following defined procedures, by peers for the purpose of identifying deficiencies and improvements. [D05196]
|
SA-CMM |
- Penalties
-
Sums to be forfeited to which the organization has agreed to be subjected in case of non-fulfillment of requirements. Typically, sums forfeited under contract for late delivery or non-performance or both. [D03131]
|
RMW |
- Penalty Power
-
The ability (of a project manager) to gain support because project personnel perceive the project manager as capable of directly or indirectly dispensing penalties that they wish to avoid, i.e. the antithesis of reward power. [D02890]
|
PMDT |
- Percent Complete
-
One measure of completion used to determine the remaining duration of a partially completed activity. [D01159]
|
WST |
-
An estimate, expressed as a percent, of the amount of work which has been completed on an activity or group of activities. [D01160]
|
PMK96 |
-
A ratio comparison of the completion status to the current projection of total work. [D01158]
|
PMK87 |
- Percent Defective
-
The percent defective of any given quantity of units of product is one hundred times the number of defective units of product contained therein divided by the total number of units of product, i.e.: Percent Defective = Number of Defectives x 100 divided by Number of Units Inspected. [D01161]
|
MIL-STD 105 QMPP |
- Percentage Complete
-
A percentage number representing the estimated amount of work in an activity that is finished. Editor's Note: The implication of this percentage complete (PC) number is that the remaining work or time is represented by 100% less the PC number. In fact Percentage Complete rarely bears a firm relationship to work or time remaining and hence is a very poor measure of progress. [D03882]
|
PNG |
- Percentage Completion
-
An assessment of how far along a task has progressed as a percentage of its total duration. As the assessment is very often subjective, it should not be relied upon as a firm basis for quantitative analysis of a project's progress. A better approach is the use of Earned Value Analysis. [D03603]
|
PMST |
- Performance
-
The calculation of achievement used to measure and manage project quality. [D01162]
|
PMK87 |
- Performance Bond
-
A bond that secures performance and fulfillment of the contractorÍs obligations under the contract. [D03542]
|
GAT |
- Performance Control
-
Control of work during contract execution. [D01163]
|
PMK87 |
- Performance Evaluation
-
The formal system by which managers evaluate and rate the quality of subordinates' performance over a given period of time. [D01164]
|
PMK87 |
- Performance Factor
-
A measure of cost performance expressed as a ratio. [D01165]
|
CPMUSC 176-8 |
- Performance Goal
-
A motivational target set by team in terms of cost and time. [D02219]
|
16 |
- Performance Management
-
A disciplined approach to the improvement of performance in organizational activities. [D03132]
|
RMW |
- Performance Measurement
-
See also Earned Value Analysis. [D03883]
|
PNG |
-
A method used to relate physical progress achieved to cost status. The method identifies whether cost variances are due to differences in the value of the work being performed, i.e. too expensive or under budget. From this, it is possible to assess whether a project is ahead, on or behind budget and whether the trend is likely to continue. [D03884]
|
PNG |
- Performance Measurement Baseline ("PMB")
-
The time-phased budget plan against which project performance is measured. It is formed by the budgets assigned to scheduled cost accounts and the applicable indirect budgets. For future effort, not planned to the cost account level, the Performance Measurement Baseline also includes budgets assigned to higher-level CWBS elements. The PMB does not include any management or contingency reserves, which are isolated above the PMB. [D01166]
|
WST |
- Performance Measurement System
-
A project planning and status system that periodically measures variances (usually cost and schedule) and requires documented corrective action to eliminate the variances that exceed predetermined thresholds. [D04171]
|
CSM |
- Performance Measurement Techniques ("PMT")
-
The methods used to estimate earned value. Different methods are appropriate to different work packages, either due to the nature of the work or to the planned duration of the work package. Another term for Performance Measurement Techniques is Earned Value Methods. [D01167]
|
WST |
- Performance Reporting
-
The collection of project performance information and its distribution. [D01168]
|
RMW |
- Performance Specification
-
Specification of required output or function. [D01169]
|
NPMT |
- Performance Standards
-
A baseline level of achievement. Commonly defined in the literature as "A standard indicates performance is satisfactory when ƒ (etc.)" Meeting a standard performance is the basic requirement for maintaining a position. Extra rewards should be bestowed only when the standard is exceeded. [D01170]
|
TML 215 |
- Performing
-
 A team building stage where the emphasis is on the work currently being performed. [D01171]
|
WST |
-
The fourth stage of Team Building where the emphasis is on the work at hand. [D03885]
|
PNG |
- Performing Organization
-
The organizational unit responsible for the performance and management of resources to accomplish a task. [D01172]
|
WST |
- Period
-
The completion of a cycle, a series of events, or a single action. Editor's Note: Also a broad term that may be applied collectively to several parts of the project life cycle. [D03133]
|
Webster |
- Period of Performance
-
The time interval of contract performance that includes the effort required to achieve all significant contractual schedule milestones. [D01173]
|
WST |
- Periodic Review
-
Any kind of project review conducted on a periodic basis, most commonly a monthly project review. [D01174]
|
SPM 304-9 |
- Periodical
-
Something that occurs or recurs at regular or intermittent intervals. [D03134]
|
RMW |
- Perpetual
-
Something that occurs continually, e.g. management activities throughout the project life cycle. [D03135]
|
RMW |
- Personal Recognition
-
The public acknowledgment of an individual's performance on the project. [D01175]
|
PMK87 |
- Personal Rewards
-
Providing an individual with psychological or monetary benefits in return for his or her performance. [D01176]
|
PMK87 |
- Personalities
-
Relationships between people, often in a disparaging context. [D03136]
|
RMW |
- Personality Types
-
A way of differentiating between people based on their characteristics, culture, attitudes, aptitudes, capabilities, skills, etc. [D03137]
|
RMW |
- Personnel
-
A body of people, those usually employed in an organization or on a team as workers or staff, etc. [D03138]
|
RMW |
- Personnel Development
-
The education and training of employees, typically the responsibility of the personnel department. [D03139]
|
RMW |
- Personnel Management
-
 An activity encompassing:
[D03451]
|
CRMP |
-
The management of an organization's employee affairs, typically the responsibility of the personnel department. [D03140]
|
RMW |
- Personnel Training
-
The development of specific job skills and techniques required by the individual to become more productive. [D01177]
|
PMK87 |
- PERT
-
See Program Evaluation and Review Technique
|
|
- PERT Analysis
-
A process by which you evaluate a probable outcome based on three scenarios:
- Best-case
- Expected-case, and
- Worst-case.
The outcome in question may be a duration of a task, its start date, or its finish date. [D01180]
|
MSP98 |
- PERT Chart
-
A flowchart that shows all tasks and task dependencies. Tasks are represented by boxes and task dependencies are represented by lines connecting the boxes. [D01181]
|
MSP98 |
-
See Project Network Diagram. [D01182]
|
|
- PERT Cost
-
A cost approach in which costs and time are estimated for each task so that the cost of making schedule changes can be evaluated. See also Program Evaluation and Review Technique. [D03081]
|
CCCP |
- Perturbation
-
Any confusion, disorder or mistake that signals a "problem". [D03667]
|
DSMC |
- Per-use Cost
-
A cost that is incurred all at once when a resource is used, such as equipment rental. [D01183]
|
MSP98 |
- Pessimistic Duration
-
The longest duration in the three duration estimating technique. [D01184]
|
WST |
|
Definitions for page P01: 50
|
|