Copyright
Wideman Comparative Glossary of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March 2002.

Please feel free to point to this document. For non-profit purposes you may copy this page, either whole or as whole definitions provided the above copyright notice is attached. For inclusion in for-profit works, please contact the author at max_wideman@sfu.ca

File: PMG_D03.htm generated 12/19/2002 9:25:36 AM
Generated by program: PMGlosGen v1.33 Program Author: Graham Wideman

Introduction | What's New in Version 5.0 | Order Your V5.0 Copy!
International Recognition 1999 | About the Author | Technical
Content Index | Sources and References

Detailed Engineering - to - Discipline

***  prev

Term
Definition     Editor's Choice
 
Source
Detailed Engineering
The phase of engineering following basic engineering after approval has been given for the project. Provides the specifications and construction drawings which detail all engineering aspects for the construction of a project. [D04966]

 SCL
Detailed Estimate
An estimate based on complete or nearly complete details of quantity, specifications, conditions and the like. Suitable for major commitments, cost tracking and control. Also known as Definitive Estimate, or "bottom up estimate". [D05158]

 RMW
Detailed Planning
The lowest level of planning adopted in a project. [D00527]

 NPMT
Detailed Plans
See Detailed Resource Plan and Detailed Technical Plan. [D00528]

  
Detailed Resource Plan
A plan implemented when it is necessary to plan and control a certain major activity within a stage. The plan sets costs and resource usage that correspond to the detailed technical plan. [D00529]

 WST
Detailed Schedule
A plan of activities for all work. The detailed schedule would typically cover activities up to at least the next major milestone. The detailed schedule supports and is consistent with the Master Schedule.
Editor's Note: See also Short Term Plan. [D02261]

 10
Detailed Technical Plan
A plan providing a detailed breakdown of selected major activities, e.g. system testing, and produced as and when required. A Detailed Technical Plan should be established on all but the very smallest projects. [D03835]

 PNG
A plan used to give a specific breakdown of major activities. It exists in all but the smallest projects. [D00530]

 WST
Determination
Arrival at a conclusion, or firm resolution to do so. [D02656]

 Webster
Determine Least Cost for Maximum Results
See Cost benefit. [D02657]

  
Deterministic
An approach that presumes the presence of fixed constraints. [D02658]

 RMW
Deterministic Network
A network with no facilities to accommodate probabilistic dependencies. Precedence networks are said to be deterministic. [D00531]

 WST
Both activity on arrow and precedence networks are said to be deterministic since they have no facilities to accommodate probabilistic dependencies. [D03836]

 PNG
Developed Country
A term used generally to refer to a country having the advanced technology of the "western world". [D02659]

 RMW
Developer
A person responsible for developing the required functionality in accordance with project-adopted standards and procedures. This can include performing activities in any of the requirements, analysis and design, implementation, and test workflows. [D04720]

 RUP
Developing Country
A term used generally to refer to a country still aspiring to the advanced technology of the "western world". [D02660]

 RMW
Development
The process of working out and extending the theoretical, practical, and/or useful application of an idea, concept, or preliminary design. [D02307]

 RMW
See Development Phase [D02180]

  
The systematic use, under whatever name, of scientific and technical knowledge in the design, development, test, or evaluation of a potential new product or service (or of an improvement in an existing product or service) for the purpose of meeting specific performance requirements or objectives. Development includes the functions of design engineering, prototyping, and engineering testing. [D03496]

 GAT
Development Case
The software-engineering process used by the performing organization. It is developed as a configuration, or customization, of the Unified Process product, and adapted to the project's needs. [D04721]

 RUP
Development Phase
The second of four sequential phases in the generic project life cycle. Also known as planning phase or definition phase. [D00533]

 PMK87
A software life cycle period that contains the activities of requirements analysis, design, coding, integration, testing, integration and acceptance support of software products. [D00532]

 08 -3
Also called the feasibility phase. That part of a project life cycle comprising feasibility studies, if required, planning, engineering or development, after which a capital appropriation request is made, supported by a project brief. See also implementation phase. [D00534]

 CCCP
Development Plan
A plan for moving a project concept to a viable project. [D02843]

 RMW
Development process
A set of partially ordered steps performed for a given purpose during software development, such as constructing models or implementing models. [D04722]

 RUP
Deviation
A departure from established requirements. Deviations occur when the work product either fails to meet or unnecessarily exceeds the requirements. [D00537]

 02 10-2
QMPP
Difference (from a project plan, budget, etc.) [D00535]

 NPMT
Written authorization, granted prior to the manufacture of an item, to depart from a particular performance or design requirement of a contract, specification, or referenced document, for a specific number of units or specific period of time. [D00536]

 04 5010.19
QMPP
Any variation from planned performance. The deviation can be in terms of schedule, cost, performance, or scope of work. Deviation analysis is the heart of exercising project control. [D03716]

 PPS&C p339
The change, plus or minus, from a control estimate or control curve. [D04967]

 SCL
A noticeable or marked departure from the appropriate norm, plan, standard, procedure, or variable being reviewed. [D05174]

 SA-CMM
Deviation Permit
See Production Permit [D01296]

  
Diagram
A graphical depiction of all or part of a model. [D04825]

 RUP
Diagramming
See scheduling. [D02661]

  
DID
See Data Item Description

  
Differences
Either
  1. Elements of disagreement or in dispute, having variations, or otherwise dissimilar, or
  2. The subtraction of one amount from another corresponding amount.
[D02662]

 RMW
Differentials
The amounts by which variable quantities differ. [D02663]

 Webster
Differing Site Conditions
Generally refers to either a subsurface or latent physical condition at the site which differs materially from the conditions shown or indicated in the contract documents. It may also include an unknown physical condition at the site, of an unusual nature, differing materially from conditions generally encountered and recognized as inherent in the work described by the contract documents. [D04968]

 PDG
Direct Cost
Any cost that is specifically identified with a particular Activity. See also Direct Project Costs [D00538]

 RMW
Direct Cost Contingency
See Project Direct Cost Contingency. [D03786]

  
Direct Costs
Costs that are specifically attributable to an activity or group of activities without apportionment. [D04426]

 APM
BS
Those costs (labor, material, and other direct costs) that can be consistently related to work performed on a particular project. Direct costs are best contrasted with indirect costs that cannot be identified to a specific project. [D00539]

 WST
Direct Labor
Labor, i.e. man-hours, that is specifically identified with a particular Activity. [D02308]

 RMW
Direct Project Costs
The costs directly attributable to a project, including all personnel, goods and/or services together with all their associated costs, but not including indirect project costs, such as any overhead and office costs incurred in support of the project. [D00540]

 PMK87
Directing
The provision of instructions with a view to achieving a project goal or objective. [D02664]

 RMW
The implementation and carrying out (through others) of those approved plans that are necessary to achieve or exceed project objectives. Generally of such broad and nonspecific nature that considerable judgment must be used in making decisions concerning the scope and frequency of demands. Directing encompasses: training; supervising; delegating; motivating; counseling; and coordinating. [D02666]

 PMDT
Direction
The way in which managers pass orders to subordinates. [D02667]

 PMDT
Directive
An instruction pursuant to a project objective. [D02665]

 RMW
Director
A level in a management hierarchy. [D04077]

 CSM
Discipline
A broad general body of knowledge, skills and competence (expertise) that logically belong together and which are required by a company in order to provide its products or service, or to provide other functions necessary for its continued existence. [D03620]

 19
The sequence of activities performed in a business that produces a result of observable value to an individual actor of the business. [D04900]

 RUP
Definitions for page D03: 51


***  prev

Home | Issacons | PM Glossary | Papers & Books | Max's Musings
Guest Articles | Contact Info | Top of Page