Legend:

OD -

Owner or Developer of project

PD -

Project Director, Owner's representative

LAC -

Lead Architect or Consultant

PCM -

Project Construction Manager

JA -

Jurisdictional Authorities

denotes primary responsibility

denotes significant supporting responsibility

Introduction | Pre-Project Study | Concept Phase
Concept Development | Schematic Design | Final Design | Tender & Award
Construction | Project Commissioning & Finishing

3.0     Project Execution Phase - cont/...

3.2.0     Stage 2 - Tender & Award

• In this stage, if a single general contract is being let, then prior to construction 'PCM' is a knowledgeable construction industry representative. Following award, the 'PCM' is the General Contractor's manager. If trade contracts are to be let, the PCM is the appointed construction manager. The following table assumes trade contracting, which gives rise to more detailed project and technical management. Otherwise, much of this work is done within the General Contractor's organization.

• At the end of this stage the owner/sponsor must select a contractor and proceed to Construction. (At this point, it should not be a question of whether or not to construct.)

Ref #

Task

Responsibility »

OD

PD

LAC

PCM

JA

3.2.1.0

     Project Management

3.2.1.1

Interview, select , & appoint Project Construction Manager (If trade contracting, an individual or firm, see note above.)

   

3.2.1.2

Establish bid package groupings

   

3.2.1.3

Bid & purchase long delivery items

   

3.2.1.4

Develop owner/tenant occupancy schedule

   

3.2.1.5

Develop detailed phased Construction Schedule

   

3.2.1.6

Finalize trade contractor bid lists

   

3.2.1.7

Analyze trade contractor markets (if necessary)

       

3.2.1.8

Conduct trade contractor pre-bid conferences

   

3.2.1.9

Regularly update & circulate Construction Schedule

   

3.2.1.10

Advise tenderers of time extensions if required

   

3.2.1.11

Receive, open & tabulate tenders

   

3.2.1.12

Analyze & verify tenders

     

3.2.1.13

Conduct pre-award post-tender discussions (if any)

     

3.2.1.14

Review & approve successful tenders

     

3.2.1.15

Prepare & issue letters of intent to proceed

     

3.2.1.16

Prepare documentation for contract signing

     

3.2.1.17

Check performance bonds

     

3.2.1.18

Review/update insurance requirements

     

3.2.1.19

Sign & issue contract documents

   

Ref #

Task

Responsibility »

OD

PD

LAC

PCM

JA

3.2.2.0

     Technical Mgt: Tender Packaging

3.2.2.1

Procure building permits (partial)

     

3.2.2.2

Prepare trade contract documents for tender packages

   

3.2.2.3

Regularly review contract plans & coordinate

     

3.2.2.4

Review and recommend on alternatives proposed

     

3.2.2.5

Receive technical questions and issue addenda (if requ'd.)

     

3.2.2.6

Technical review of tenders & make recommendations

   

Final Design  Final Design

Home | Issacons | PM Glossary | Papers & Books | Max's Musings
Guest Articles | Contact Info | Search My Site | Site Map | Top of Page