This Guest paper was submitted for
publication and is Copyright M. Abdomerovic (2005)
|
|
Other Research
As a part of this study, we conducted other research by way of comparison. The
results are shown in Tables 1 and 2 below.
| Parameter |
Integr'n |
Scope |
Time |
Cost |
Quality |
Human
Res's |
Comm's |
Risk |
Proc't |
Total |
1996 Edition
Processes |
3 |
5 |
5 |
4 |
3 |
3 |
4 |
4 |
6 |
37 |
2000 Edition
Processes |
3 |
5 |
5 |
4 |
3 |
3 |
4 |
6 |
6 |
39 |
2004 Edition
Processes |
7 |
5 |
6 |
3 |
3 |
4 |
4 |
6 |
6 |
44 |
2000 Edition
The Same Input
Sets as in 1996 |
2 |
4 |
1 |
1 |
3 |
3 |
4 |
0 |
6 |
24 |
2000 Edition
The Same Output
Sets as in 1996 |
3 |
3 |
5 |
3 |
3 |
3 |
2 |
0 |
6 |
28 |
2004 Edition
The Same Input
Sets as in 2000 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2004 Edition
The Same Output
Sets as in 2000 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
1 |
3 |
1996 Edition
Inputs |
12 |
19 |
30 |
18 |
12 |
11 |
13 |
13 |
12 |
140 |
1996 Edition
Outputs |
7 |
12 |
15 |
10 |
10 |
8 |
7 |
13 |
12 |
94 |
2000 Edition
Inputs |
13 |
22 |
33 |
22 |
12 |
11 |
13 |
40 |
20 |
186 |
2000 Edition
Outputs |
7 |
14 |
15 |
11 |
10 |
8 |
9 |
25 |
12 |
111 |
2004 Edition
Inputs |
35 |
25 |
38 |
21 |
21 |
19 |
14 |
25 |
30 |
228 |
2004 Edition
Outputs |
28 |
21 |
32 |
16 |
20 |
12 |
13 |
13 |
23 |
178 |
Table 1: Comparison of knowledge area content of successive Guides
| Parameter |
1996 Edition |
2000 Edition |
2004 Edition |
|
Pages (Including Front Pages)
|
182 |
224 |
396 |
|
% Blank Pages
|
12.8 |
12.5 |
10.5 |
|
Average Characters / Line
|
77 |
77 |
77 |
|
Average Line / Page
|
50 |
50 |
45 |
|
Relative Number of Pages
|
182 |
224 |
377 |
|
% Increase
|
Base (182) |
23 |
68 |
| Processes |
37 |
39 |
44 |
| Inputs |
140 |
186 |
228 |
| Outputs |
94 |
111 |
178 |
| The Same Input Sets As in predecessor edition |
Base (37) |
24 |
0 |
| The Same Output Sets As in predecessor edition |
Base (37) |
28 |
3 |
| Outputs with the same name, which have been created with different sets of inputs |
7 |
6 |
19 |
| Reappearance of outputs with the same name |
25 |
23 |
98 |
Table 2: Analysis & comparison of key elements of successive Guides
|
|