| Appendix 1Definitions and Formulae adopted in this paper Production (Rate)The rate at which units are produced over a given period of time, independent 
 of the number of man-hours consumed. ProductivityIn its broadest form, productivity may be described as a measure of how well 
 the resources in a firm are brought together and used to accomplish a set of 
 results.[7] In its simplest form, it may 
 be expressed as the ratio of output to input or the actual rate of output or 
 production per unit of time worked.[8] 
 These represent measures of production efficiency. When measurements are taken 
 over a given period of time, the period productive efficiency is the number of 
 units produced in that time period divided by the number of man-hours to do so. S-curveWhen the cumulative total of on-going work on a construction job is plotted 
 against time, the resulting curve typically follows the shape of the letter "S". 
 It is more generally referred to as a Progress Curve. Learning or Experience CurvesStudies have shown that the change in cost associated with a change in productivity 
 has, in many situations, a characteristic curve that can be estimated with reasonable 
 accuracy. This is called the "learning curve" or "experience 
 curve".[9] The underlying phenomenon is that skill and productivity in performing tasks 
 improve with experience and practice and there are a number of different ways 
 of plotting this relationship that facilitate mathematical analysis. Two models 
 of Learning Curves are given in Appendix 2, Learning Curve Mathematics. Well-runA well-run construction job implies that adequate and realistic planning has 
 taken place and a positive cultural environment has been established for the 
 performance of the work on site. It also means that supporting logistics, including 
 delivery of materials and equipment, have been properly assessed and will be 
 provided when needed to enable optimized crew sizes to maximize their production 
 at least cost at each point in time. It follows that the resulting project should 
 be perceived as successful in terms of meeting requirements and being completed 
 within credible time and cost parameters. For an owner this would mean that the 
 resulting facility has satisfied the stipulated needs, within reasonable time 
 and budget. For a contractor, it would mean satisfying the owner at a profit. In contrast, actual progress on a not-so-well-run job will depart from the 
 plan or proceed as "a voyage of discovery". The records will likely 
 reflect wasted manpower before sufficient work is available or after it is substantially 
 completed, lower productivity, higher manpower turnover, additional learning 
 costs, added supervision, labour and non-labour-related job expenses and overhead, 
 added material storage, handling and wastage, and extended completion. Standard Resource Input curve (SRI S-curve) Points on the SRI S-curve may be determined as follows: 
 Standard Production Output curve (SPO S-curve) Points on the SPO S-curve may be determined as follows: 
 7. Cleland, 
  D. I. 1990. Project Management Strategic Design and Implementation. TAB Books 
  Inc. Blue Ridge Summit, Pennsylvania. 344.
 8. Cleland, D. I. and Kerzner H. 1985. A Project Management dictionary of 
  Terms. Van Nostrand Reinhold C. New York. 193.
 9. Anthony, R. N. and Reece, J. S. 1975. Management Accounting: Text and Cases.Richard D. Irwin, Inc., Homewood, Illinois. 540.
 |