This paper was originally authored by Greg Gendall of Midori Media in May 2003.
It has since been revised and updated by the present author.


This 4th Edition was submitted for publication in January 2019.
It is copyright © Midori Media. 
Published here July 2019.

Editor's Note and Introduction | What is an S‑curve? 
Types of S‑curvesBaseline, Target, Actual, Man Hours vs Time
Cost vs Time | Value and Percentage | PART 2

Types of S-curves —Value and Percentage S-curves

S-curves may be graphed as absolute values (i.e. Man Hours or Cost) versus Time, or as percentage values versus Time.

Value S-curves

Value S-curves are useful for determining the Project's Man Hours or Cost expended to date, and Man Hours or Cost to complete.

Figure 5: Value Baseline, Actual, and Target Man Hours versus Time S-curves
Figure 5: Value Baseline, Actual, and Target Man Hours versus Time S‑curves

Analysis of the above S-curves reveals the Project as of the 4th of February 2016:

  • Is 10.5 Man Hours behind schedule (48.5 – 38.0)
  • Has grown in scope by 5.0 Man Hours (95.0 – 90.0)
  • Has increased in Duration by 1 Day
  • Started 1 Day late
  • Will finish 2 Days late
  • Will require 57.0 Man Hours to complete (95.0 – 38.0)

Percentage S-curves

Percentage S-curves are useful for comparing the Project's performance to either the Baseline and/or Production Schedule.

Percentage S-curves (Baseline = 100%)

By setting the Baseline S-curve to finish at 100%, the Project's percentage growth (or contraction) may be compared to the Baseline Schedule, and the Baseline % Complete as of the Cut Off Date may be determined.

Figure 6: Percentage Man Hours versus Time (Baseline = 100%) S-curves
Figure 6: Percentage Man Hours versus Time (Baseline = 100%) S‑curves

Analysis of the above S‑curves reveals the Project as of the 4th of February 2016:

  • Has grown in scope by 5.56% (105.56 – 100.00)
  • Was planned to be 86.67% complete

Percentage S-curves (Target = 100%)

By setting the Target S-curve to finish at 100%, the Project's Actual % Complete may be compared to the Target % Complete as of the Cut Off Date.

Figure 7: Percentage Man Hours versus Time (Target = 100%) S-curves
Figure 7: Percentage Man Hours versus Time (Target = 100%) S‑curves

Analysis of the above S‑curves reveals the Project as of the 4th of February 2016 is:

  • 11.05% behind target (51.05 – 40.00)

In Part 2 of this paper, I will describe how an S-curve is generated.

Types of S-curves - Cost vs Time  Types of S‑curves — Cost vs Time

Home | Issacons | PM Glossary | Papers & Books | Max's Musings
Guest Articles | Contact Info | Search My Site | Site Map | Top of Page