This paper was originally authored by Greg Gendall of Midori Media in May 2003.
It has since been revised and updated by the present author.


This 4th Edition was submitted for publication in January 2019.
It is copyright © Midori Media.
Published here September 2019.  

PART 2 | Worked Example | Generating Percentage S‑curves
Using Task Duration as a Quantity | PART 4

Using Task Duration as a Quantity

Extreme caution should be exercised when using Task Duration as a quantity to generate S‑curves.

Consider the following Production Schedule.

Task Name

Start

Finish

Man Hours

% Complete

Duration

MH per Day

Task No. 1

01‑Feb‑2016

05‑Feb‑2016

10.0

40%

5

2.0

Task No. 2

02‑Feb‑2016

05‑Feb‑2016

20.0

30%

4

5.0

Task No. 3

03‑Feb‑2016

05‑Feb‑2016

30.0

20%

3

10.0

Task No. 4

04‑Feb‑2016

05‑Feb‑2016

140.0

0%

2

70.0


Totals

 

 

200.0

 

14

 

Table 12: Production Schedule

The % Complete values represent the Task's physical percentage completion, as inspected on 4th February 2016 (The Cut Off Date).

Task Duration S-curves

The S-curves generated using Task Duration as the Quantity are shown in Figure 20.

Figure 20: Percentage Task Duration S-curves (Target = 100%)
Figure 20: Percentage Task Duration S-curves (Target = 100%)

Analysis of the above S-curves reveals the Project as of the 4th of February 2016:

  • Is 27.86% Complete (Actual)
  • Should be 42.86% Complete (Target)
  • Is 15.00% behind target (42.86 - 27.86)

Task Man Hour S-curves

The S-curves generated using Task Man Hours as the Quantity are shown in Figure 21.

Figure 21: Percentage Task Man Hours S-curves (Target = 100%)
Figure 21: Percentage Task Man Hours S-curves (Target = 100%)

Analysis of the above S-curves reveals the Project as of the 4th of February 2016 is:

  • 7.95% Complete (Actual)
  • Should be 13.00% Complete (Target)
  • 5.05% behind target (13.00 - 7.95)

A comparison of the above figures reveal using Task Duration as a quantity paints a very different picture of the Project's progress as compared to using Task Man Hours as a quantity.

The reason for the variance in the Project's progress is that by using Task Duration as a quantity, the assumption is all Tasks require exactly the same amount of Man Hours per Day. This is often not the case in real life.

In Part 4 I will justify why S-curves are so important as a reporting tool

Generating Percentage S-curves  Generating Percentage S‑curves

Home | Issacons | PM Glossary | Papers & Books | Max's Musings
Guest Articles | Contact Info | Search My Site | Site Map | Top of Page