| Baselines and Freezes at Milestones 3 and 4The standard against which design choices are evaluated and controlled is the 
approved set of requirements: the scope baseline shown at milestone 3 on the life 
cycle diagram. At this point in the life of the project, a feasibility study has 
been conducted. A concept or a system has been chosen from among the alternatives 
that could satisfy the need for change, originally expressed as a problem or an 
opportunity. The requirements statement should make specific reference to a chosen 
concept. For example, a bridge may be chosen as the preferred device for moving 
vehicles across a river, instead of a tunnel, a causeway, or a fleet of ferryboats. 
The requirements statement should set out the requisite characteristics of the 
bridge. It should not attempt to be a generalized description of the functional 
capabilities of all possible modes of conveyance. In the architectural field, the preparation of requirements statements is a 
specialized discipline called functional and space programming. An architectural 
program provides a definitive statement of the requirements to be addressed by 
the designer by specifying the spatial, functional, technical, and operational 
capabilities of the facility. If properly done, the program is expressed in non-technical 
terms that are clearly understood by the users, or beneficiaries, of the facility. In his listing of the programming information required to establish a capital 
cost estimate at this stage of a project, Parker calls for a description of the 
client's need for the facility in relation to market or business strategy, the 
business or operational objectives for the end product, and specific objectives 
to be realized in the design itself.[70] 
Under each category, he lists illustrative items. Parker further identifies functional 
space, occupancy, and special systems and features as three categories of information, 
normally obtained from an architectural program, that are key determinants of 
the project cost. He gives a useful checklist of items in each category.[71] Smythe provides a checklist of 37 items that can serve as a starting point 
for developing a requirements statement for an industrial plant project. He groups 
the items under the headings of process, services, environment, maintenance, security, 
safety, and regulatory.[72] Webster's listing of the possible sub-dimensions of scope (technical performance) 
is illustrated with examples from the automotive industry. His nine categories, 
however, suggest a framework for developing a requirements statement for other 
manufactured products, under the headings: physical criteria, performance, reliability, 
unit cost of production, capital cost for production facilities, maintenance cost 
in use, unit operating cost, aesthetic features, and esoteric criteria expectations 
which exceed reasonable form and function requirements.[73] Once the requirements statement has been approved by the client or sponsor, 
the project team develops a more elaborate conceptual design. The deliverable 
at milestone 4 on Figure 2 assigns the agreed 
requirements to major functional components or subsystems of the end product. 
In the case of a building, Parker indicates the initial design decisions are concerned 
with configuration (massing, number of floors, footprint, site plan) and design 
parameters by system (structural, mechanical, electrical, plumbing).[74] 
In the terminology of defense materiel procurement, the system at this point has 
been subdivided into configuration items, and a specification of functional performance, 
design requirements, and interface requirements has been prepared for each item. 
The deliverable, once reviewed and approved, constitutes the "functional baseline." At milestone 4, the project outline or functional baseline, if it is compliant 
with the statement of requirements, is formally "frozen." That is to say, the 
design decisions taken to date must be respected in all subsequent design work. 
The functional baseline is the fixed framework within which future design choices 
must be made. The project outline document illustrated in Figure 
2 shows a WBS consisting only of summary level scope elements. Each of the 
chosen subsystems or components in the design is represented by a corresponding 
WBS element. 70. Parker, 
D.E. Defining Project Scope for Effective Cost Control. Cost Engineer's Notebook 
Index No. B 4.202, Rev. 1, 3/87. This item is contained in Cost Engineering 29.3, 
March 1987, p3
 71. Ibid, p6-9
 72. Smythe, E.B. The Project Management Process Copies of overhead 
transparencies used in a seminar, Vancouver, B.C.: Executive Programs, the University 
of British Columbia, 1981, pp50-51
 73. Webster, F.M., Jr. Micro Characteristics of an Activity and 
its Performance. Proceedings of the 1979 Seminar Symposium Drexel Hill, PA: The 
Project Management Institute, 1979, p360
 74. Parker, D.E. Defining Project Scope for Effective Cost Control. 
Cost Engineer's Notebook Index No. B 4.202, Rev. 1, 3/87. This item is contained 
in Cost Engineering 29.3, March 1987, pp8-10
 
 |